Projects
This is a full list of the energy projects that are being pursued or are needed in Southwest Alaska communities. If the page isn’t wide enough to show all fields, click the green “+” dot to the left of each row to show the hidden data. This list has been compiled through the AEA Regional Energy Planning effort and through contact with regional stakeholders and it is continually being updated. For more detail on these projects, contact Laura Vaught.
Use the search box below to filter the table to show only specific projects, resources, communities, or regions.
Region
|
Community
|
Resource
|
Project Name
|
Description
|
Project Status
|
Project Stage
|
Project Lead Org
|
---|---|---|---|---|---|---|---|
Aleutians | Adak | Energy Infrastructure | Add additional community facilities to PCE program | Identify additional community facilities for PCE enrollment | Issue/Need | Need Identified | |
Aleutians | Adak | Energy Infrastructure | Power System Upgrade – generators, transformers, transmission lines. | Rural Power System Upgrade: Replace, upgrade, and properly scale existing grid, generators, transmission lines, and transformers to right-size system, improve diesel efficiency, and address high line losses. | Active Project | Repair & Upgrade | City of Adak, TDX Power |
Aleutians | Adak | Geothermal | Explore geothermal potential | Issue/Need | Monitor Developments | ||
Aleutians | Adak | Hydroelectric | Install small hydroelectric turbine at Bonnie Rose Lake | Assess feasibility of adding hydroelectric infrastructure at existing dams (such as Bonnie Rose). | Active Project | Reconnaissance & Feasibility | TDX Adak Generating |
Aleutians | Adak | Management | Next generation utility workforce development | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | Adak | Space Heating | Space heating for community buildings | Explore space heating options for community buildings | Issue/Need | Not Operational | |
Aleutians | Adak | Tidal | Tidal | TDX Power is investigating possible tidal resource at Clam Lagoon. | Issue/Need | Monitor Developments | TDX Power |
Aleutians | Adak | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Aleutians | Adak | Wind | Install MET tower at less turbulent site. | Active Project | Reconnaissance & Feasibility | ||
Aleutians | Akutan | Energy Efficiency | Energy efficiency upgrades | Light bulb project (?). Want EE in public and private buildings. | Active Project | Reconnaissance & Feasibility | City of Akutan |
Aleutians | Akutan | Energy Infrastructure | Address high line loss. | Issue/Need | Need Identified | ||
Aleutians | Akutan | Energy Infrastructure | Add additional community facilities to PCE program | Issue/Need | Need Identified | ||
Aleutians | Akutan | Geothermal | Geothermal Development | Akutan Geothermal Development Final Design | Active Project | Reconnaissance & Feasibility | City of Akutan |
Aleutians | Akutan | Heat Recovery | Install heat recovery system | Potential heat recovery to buildings near powerplant. | Issue/Need | Need Identified | |
Aleutians | Akutan | Hydroelectric | Town Creek Hydro, 105 kW | Work Complete | Operational | City of Akutan | |
Aleutians | Akutan | Management | O&M training to maintain hydro facility long-term | ||||
Aleutians | Akutan | Management | Start training next generation of utility workforce | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | Akutan | Solar | Solar PV | Potential resource feasibility | Issue/Need | Reconnaissance & Feasibility | |
Aleutians | Akutan | Tidal | Monitor tidal and wave power technology development | Monitor tidal and wave power demonstration projects and technology development. | Issue/Need | Monitor Developments | |
Aleutians | Akutan | Transportation | Add trans-load dock and build access road between village and harbor | Issue/Need | Need Identified | City of Akutan | |
Aleutians | Akutan | Transportation | Improve runway on Akun Island | Issue/Need | Need Identified | City of Akutan | |
Aleutians | Atka | Bulk Fuel | Investigate other bulk fuel delivery options | Issue/Need | Need Identified | City of Atka | |
Aleutians | Atka | Energy Infrastructure | Address line loss | Address cause of moderate line loss (6-11%) | Issue/Need | Need Identified | |
Aleutians | Atka | Energy Infrastructure | Improve diesel efficiency to bring up to AEA benchmark for small utilities | Issue/Need | Need Identified | ||
Aleutians | Atka | Heat Recovery | Study feasibility of powerhouse heat recovery | Issue/Need | Reconnaissance & Feasibility | ||
Aleutians | Atka | Hydro to Heat | Atka Dispatchable Heat design and construction | Install dispatchable boilers to use excess electricity from hydro facility to heat community buildings | On Hold | Final Design & Construction | City of Atka |
Aleutians | Atka | Hydroelectric | Connect Chuniisax Creek hydro to APICDA's Atka Pride Seafoods plant | Hydropower is currently not being fully utilized by only being connected to city load. Potential to connect to fish plant to fully utilize hydro. | Active Project | Reconnaissance & Feasibility | City of Atka, APICDA |
Aleutians | Atka | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | Atka | Solar | Solar-powered streetlights for dock and bulk fuel facility | Work Complete | Operational | City of Atka | |
Aleutians | Atka | Space Heating | Assess renewable energy options for residential heating | Issue/Need | Need Identified | City of Atka | |
Aleutians | Atka | Transportation | Runway improvements | Issue/Need | Need Identified | City of Atka | |
Aleutians | Atka | Wind | Study wind resource | MET towers installed in August 2015, currently collecting data. | Active Project | Reconnaissance & Feasibility | APICDA |
Aleutians | Cold Bay | Bulk Fuel | City fuel farm | Feasibility and conceptual design of city fuel farm. | Reconnaissance & Feasibility | ||
Aleutians | Cold Bay | Energy Infrastructure | Improve efficiency of diesel generators | Improve diesel efficiency to bring up to AEA benchmark of 14.5 kWh/gallon for utilities producing over 2,000 MWh/year. FY14 efficiency was 13.4 kWh/gallon. | Issue/Need | Need Identified | |
Aleutians | Cold Bay | Energy Infrastructure | Address moderate line loss | Address causes of moderate line loss (8% in FY14) | Issue/Need | Need Identified | |
Aleutians | Cold Bay | Heat Recovery | District heating loop for government buildings | Waste Heat Recovery Feasibility and Conceptual Design. Assess feasibility of a district heating loop for government buildings. | Active Project | Reconnaissance & Feasibility | G&K Electric Utility / Aleutians East Borough |
Aleutians | Cold Bay | Hydroelectric | Run-of-river project on Russell Creek | Assess feasibility of run-of-river project on Russell Creek or other steams. | Issue/Need | Need Identified | G&K Electric Utility |
Aleutians | Cold Bay | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | Cold Bay | Other Critical Community Need | Develop protected marine infrastructure, increased USCG & Arctic activity | Develop protected marine infrastructure. Monitor increased activity in Cold Bay related to USCG expansion and Arctic activity (oil and gas, shipping, etc.). | Issue/Need | Monitor Developments | City of Cold Bay |
Aleutians | Cold Bay | Tidal | Tidal and wave power demonstration projects | Monitor tidal and wave power demonstration projects and technology development. | Issue/Need | Monitor Developments | |
Aleutians | Cold Bay | Wind to Heat | Wind-to-Heat project | Revisit failed vertical axis turbines in Cold Bay wind-to-heat project | On Hold | Not Operational | G&K Electric Utility (IPP) |
Aleutians | False Pass | Energy Infrastructure | Address moderate line loss | Address cause of moderate line loss (6-11%) and diesel efficiency | Issue/Need | Need Identified | City of False Pass |
Aleutians | False Pass | Heat Recovery | Heat recovery system installed, investigate connection to school | Active Project | Reconnaissance & Feasibility | City of False Pass | |
Aleutians | False Pass | Hydroelectric | Unga Man Creek, 125 kW run-of-river | Feasibility study of potential 125 kW run-of-river resource on Unga Man Creek | Active Project | Reconnaissance & Feasibility | City of False Pass |
Aleutians | False Pass | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | False Pass | Tidal | TidGen project in Isanotski Strait | Hydrokinetic Feasibility and Conceptual Design for ORPC TidGen project in Isanotski Strait | Active Project | Reconnaissance & Feasibility | City of False Pass |
Aleutians | False Pass | Wind | Wind resource assessed; power system upgrades needed | Finish Met tower data collection and submit feasibility report. | Active Project | Reconnaissance & Feasibility | City Utility |
Aleutians | King Cove | Energy Infrastructure | Address high line loss | Address causes of high line loss (17% in FY14) | Issue/Need | Need Identified | |
Aleutians | King Cove | Heat Recovery | Extend heat recovery system to Community Center | Extend heat recovery system to Community Center (if center is converted to a Senior Living facility). | Issue/Need | Repair & Upgrade | |
Aleutians | King Cove | Hydroelectric | Waterfall Creek hydro – 375 kW run-of-river | 375 kW run-of-river Waterfall Creek hydro completed with transmission to existing Delta Creek hydro powerhouse | Work Complete | Operational | City of King Cove |
Aleutians | King Cove | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development. | Issue/Need | Need Identified | |
Aleutians | King Cove | Other Critical Community Need | Power Purchase Agreement with Peter Pan to sell surplus power | Issue/Need | Need Identified | ||
Aleutians | King Cove | Wind | Identify new Met tower site(s) in Delta Creek Valley | Identify new Met tower site(s) in Delta Creek Valley and do feasibility study. Monitor technology to find best system for strong winds. | Issue/Need | Monitor Developments | |
Aleutians | Nelson Lagoon | Biomass | Assess wood biomass resource for community-scale project | Conduct pre-feasibility assessment of whether sufficient wood biomass exists for community-scale project | Issue/Need | Reconnaissance & Feasibility | Tribal Council |
Aleutians | Nelson Lagoon | Energy Efficiency | Energy efficiency upgrades in public buildings | Energy efficiency upgrades, including LED lighting, in public buildings. | |||
Aleutians | Nelson Lagoon | Energy Infrastructure | Replace or overhaul one generator | Secure funding to replace or overhaul one generator. | Issue/Need | Repair & Upgrade | |
Aleutians | Nelson Lagoon | Energy Infrastructure | Improve efficiency of diesel generators | Improve diesel efficiency to AEA benchmark level for small utilities of 12.5 kWh/gallon. | Issue/Need | Need Identified | |
Aleutians | Nelson Lagoon | Energy Infrastructure | Address high line loss | Address high line loss (12% in FY14) through upgrade of distribution system and replacement of transformers that are beyond useful life. | Issue/Need | Need Identified | Tribal Council |
Aleutians | Nelson Lagoon | Heat Recovery | Investigate heating Nelson Lagoon Storage Building with heat recovery system | Assess feasibility of waste heat for Nelson Lagoon Storage Building, owned by APICDA. It appears that the power plant produces enough waste heat to cover it. | Issue/Need | Need Identified | |
Aleutians | Nelson Lagoon | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development | Issue/Need | Need Identified | |
Aleutians | Nelson Lagoon | Solar | Community-scale solar | Assess feasibility of community-scale solar. | Issue/Need | Need Identified | |
Aleutians | Nelson Lagoon | Tidal | Monitor tidal power developments | Monitor tidal power technology developments for potential future project under dock | Issue/Need | Monitor Developments | Tribal Council |
Aleutians | Nelson Lagoon | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Aleutians | Nelson Lagoon | Wind | Wind project, complete avian study and CDR | APIA completed avian study and drafted Concept Design Report (CDR) based on data collected from modified 40’ monopole tower. | Active Project | Design | Nelson Lagoon Electric Cooperative |
Aleutians | Nikolski | Energy Infrastructure | Replace boilers | Tribe paid for new boilers for community homes. | Work Complete | Repair & Upgrade | Native Village of Nikolski |
Aleutians | Nikolski | Energy Infrastructure | New generator | Nikolski needs a new generator | Issue/Need | Need Identified | |
Aleutians | Nikolski | Energy Infrastructure | Address moderate line loss | Address causes of moderate line loss (6% in FY2014) | Issue/Need | Need Identified | |
Aleutians | Nikolski | Energy Infrastructure | Improve efficiency of diesel generators | Improve diesel efficiency to AEA benchmark level for small utilities of 12.5 kWh/gallon. FY14 diesel efficiency in Nikolski was 9.9 kWh/gallon. | Issue/Need | Need Identified | |
Aleutians | Nikolski | Heat Recovery | Heat recovery system at powerhouse | Heat recovery system is installed at powerhouse. | Work Complete | Operational | |
Aleutians | Nikolski | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development | Issue/Need | Need Identified | |
Aleutians | Nikolski | Solar | Solar PV | Assess resource and possible integration with grid | Active Project | Reconnaissance & Feasibility | |
Aleutians | Nikolski | Wind | Fix stagnant wind turbine, integrate with powerplant | Turbine needs to be fixed to be made operational again. Powerplant controls need work before integration. | Issue/Need | Not Operational | |
Aleutians | Saint George | Bulk Fuel | Fuel storage sharing with St. Paul | Share fuel storage with St. Paul through inter-island ferry | Issue/Need | Need Identified | |
Aleutians | Saint George | Bulk Fuel | Upgrade tank farm | Tank farm upgrades | Scheduled | Design | City of St. George |
Aleutians | Saint George | Energy Infrastructure | Rural Power System Upgrade | Rural Power System Upgrade project to upgrade existing diesel system | Active Project | Installation | AEA |
Aleutians | Saint George | Heat Recovery | Heat recovery system | The powerhouse has a waste heat recovery system installed. It heats the school, city offices, and public safety building. | Work Complete | Operational | City of St. George |
Aleutians | Saint George | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development | Issue/Need | Need Identified | |
Aleutians | Saint George | Other Critical Community Need | Identify funds for construction of 10 new homes | Explore sources of funding for construction of 10 new homes | Issue/Need | Need Identified | |
Aleutians | Saint George | Other Critical Community Need | Demolition and removal of old homes | Complete plan for demolition and removal of older, federally constructed homes that contain lead paint. | Scheduled | Design | |
Aleutians | Saint George | Solar | Community-scale solar | Assess feasibility of community-scale solar. | Issue/Need | Monitor Developments | City of St. George |
Aleutians | Saint George | Transportation | Harbor reconstruction and dredging | Harbor reconstruction and dredging | Issue/Need | Need Identified | City of St. George |
Aleutians | Saint George | Wind | Wind Farm Construction/Wind Turbine Replacement | St. George Wind Farm Construction / Wind Turbine Replacement | Active Project | Installation | St. George, AEA's Wind & RPSU Programs |
Aleutians | Saint Paul | Bulk Fuel | Upgrade tank farm | Issue/Need | Need Identified | AEA | |
Aleutians | Saint Paul | Bulk Fuel | Fuel storage sharing with St. George | Share fuel storage with St. George through inter-island ferry. Install new tanks for aviation fuel at or near St. Paul airport | Issue/Need | Need Identified | City of St. Paul |
Aleutians | Saint Paul | Energy Efficiency | EE retrofits to public buildings | EE/heating/lighting/insulation/weatherization and repairs to City Hall, Public Works building, Civic Center, and city transient housing. Continue replacement of street lighting to LED fixtures. | Active Project | Repair & Upgrade | |
Aleutians | Saint Paul | Energy Infrastructure | Rural Power System Upgrade | Rural Power System Upgrade; Add emergency generation for homes and essential services | Issue/Need | Need Identified | City of St. Paul |
Aleutians | Saint Paul | Energy Infrastructure | Address high line loss | 14% line loss | Issue/Need | Need Identified | |
Aleutians | Saint Paul | Energy Infrastructure | Improve efficiency of diesel generators | Improve diesel efficiency to AEA benchmark of 14.5 kWh/gallon for utilities producing over 2,000 MWh/year. FY14 diesel efficiency was 13.9 kWh/gallon | Issue/Need | Need Identified | |
Aleutians | Saint Paul | Energy Infrastructure | Maintenance training of local personnel on high voltage distribution system | Funding for on-site training of local personnel in safe High Voltage distribution system maintenance | Issue/Need | Need Identified | |
Aleutians | Saint Paul | Heat Recovery | Upgrade heat recovery loop to integrate with wind-diesel system | Design upgrade and extension of heat recovery loop to work with wind-diesel system. | Active Project | Design | City Utility |
Aleutians | Saint Paul | Storage of Renewables | Flywheel for excess wind electricity storage | On Hold | Not Operational | TDX Corp. | |
Aleutians | Saint Paul | Water/Sewer | Retrofits of sewer lift station | Existing sewer lift station retrofits would benefit from increased safety and reduced energy consumption through pump optimization | Issue/Need | Repair & Upgrade | |
Aleutians | Saint Paul | Wind | Integrate existing TDX wind turbines into the City power grid | Integrate power from existing TDX wind turbines onto the City grid after necessary upgrades to the powerhouse and transmission system are made to address load stability issues. Extend wind power to City landfill. | Active Project | Operational | |
Aleutians | Saint Paul | Wind | TDX Power Grant Project: Energy retrofits & wind turbine at airport | Project will reduce energy consumption at airport by 54% through energy retrofits, and increase the contribution of wind from 35% to 65% by installing another 900 kW wind turbine. | Active Project | Installation | TDX Power |
Aleutians | Saint Paul | Wind | St. Paul Wind Diesel System | St. Paul Wind Diesel Construction | Work Complete | Operational | TDX Corp. |
Aleutians | Saint Paul | Wind to Heat | EE & Reuse energy at POSS camp | TDX: Electric boiler on their POSS Camp. Doing analysis on wasted POSS energy: make more EE, use some of excess energy for thermal, maybe heat school and city office, boiler or heat pump. | Active Project | Reconnaissance & Feasibility | TDX Power |
Aleutians | Sand Point | Bulk Fuel | Add bulk fuel tanks | Reassess feasibility of additional bulk fuel tanks to offer alternative pricing | Issue/Need | Need Identified | |
Aleutians | Sand Point | Energy Infrastructure | Upgrade existing diesel system | Upgrade existing diesel system. Improve diesel efficiency to bring up to AEA benchmark of 14.5 kWh/gallon for utilities producing over 2,000 MWh/year. FY2014 diesel efficiency was 13.9 kWh/gallon. | Issue/Need | Need Identified | |
Aleutians | Sand Point | Energy Infrastructure | Add community facilities to PCE program | Identify additional community facilities for PCE enrollment | Issue/Need | Need Identified | |
Aleutians | Sand Point | Heat Recovery | Limited heat recovery system | Limited heat recovery system operational | Work Complete | Operational | |
Aleutians | Sand Point | Hydroelectric | Hydro resource at Humboldt Slough | Feasibility study at Humboldt Slough | |||
Aleutians | Sand Point | Management | AEA utility operator successor training | Look into AEA utility operator successor training program for next generation workforce development | Issue/Need | Need Identified | |
Aleutians | Sand Point | Other Critical Community Need | Investigate selling power to Trident Seafood plant | Assess opportunity for selling power to Trident seafood plant | Issue/Need | Need Identified | |
Aleutians | Sand Point | Storage of Renewables | Sand Point Energy Storage for excess wind energy | Sand Point Energy Storage Design & Construction: Install an inverter and battery bank to store excess wind energy. | Active Project | Need Identified | TDX Sand Point Generating |
Aleutians | Sand Point | Water/Sewer | Find funding to implement sanitation system EE retrofits. | Issue/Need | Installation | City of Sand Point | |
Aleutians | Sand Point | Wind | Expand wind capacity | Expand wind capacity. | Issue/Need | Need Identified | TDX Sand Point Generating |
Aleutians | Sand Point | Wind | Two 500 kW wind turbines | Two wind turbines installed | Work Complete | Operational | Aleutian Wind Energy (IPP) |
Aleutians | Sand Point | Wind to Heat | Sand Point Excess Wind Utilization | Sand Point Excess Wind Utilization | Scheduled | Installation | TDX Sand Point Generating |
Aleutians | Sand Point | Wind to Heat | Wind to heat (boilers or heat pumps) | Feasibility Wind to heat (boilers or heat pumps). Grant with DOE to design micro grid controller with fast dispatchable loads. | Active Project | Reconnaissance & Feasibility | TDX Sand Point Generating |
Aleutians | Unalaska | Biomass | Solid waste incineration for biomass energy production | Study the use of solid waste incineration for biomass energy production | Issue/Need | Need Identified | City of Unalaska |
Aleutians | Unalaska | Energy Infrastructure | Add community facilities to PCE program | Identify additional community facilities for PCE enrollment | Issue/Need | Need Identified | |
Aleutians | Unalaska | Energy Infrastructure | Integrate private powerhouses (local fish plants) into the city grid | Integrate private powerhouses (local fish plants) into the city grid | Active Project | Need Identified | City of Unalaska |
Aleutians | Unalaska | Geothermal | Makushin Geothermal Site | Makushin Geothermal Site | Previously Considered | Monitor Developments | City of Unalaska |
Aleutians | Unalaska | Heat Pumps | Heat pump feasibility | Heat pump feasibility – Study costs and benefits of heat pumps for space heating. | Issue/Need | Monitor Developments | City of Unalaska |
Aleutians | Unalaska | Heat Recovery | Increase buildings connected to heat recovery system | Expand number of buildings heated with waste heat and increase overall power production with ORC when new powerhouse is constructed. | Issue/Need | Reconnaissance & Feasibility | City of Unalaska |
Aleutians | Unalaska | Hydroelectric | Assess hydro potential at Pyramid Creek (260 kW), Shaishnikof Creek (700 kW), and Kacie Lake | Update feasibility assessment of potential sites at Pyramid Creek (260 kW), Shaishnikof Creek (700 kW), and Kacie Lake. | Active Project | Reconnaissance & Feasibility | City of Unalaska |
Aleutians | Unalaska | Natural Gas | LNG generator & LNG pipeline, storage, and distribution | Conclude performance testing of LNG generator and feasibility study of importing LNG by tanker. Design of LNG pipeline, storage & distribution system | Active Project | Reconnaissance & Feasibility | City of Unalaska |
Aleutians | Unalaska | Solar | Small Solar PV demonstration project | City Manager wants to put in a small Solar PV demonstration project. | Active Project | Reconnaissance & Feasibility | City of Unalaska |
Aleutians | Unalaska | Transportation | Unalaska Marine Center dock project | Complete UMC dock project | Active Project | Final Design & Construction | City of Unalaska |
Aleutians | Unalaska | Transportation | Lengthen and widen runway | Lengthen and widen the runway | Issue/Need | Need Identified | City of Unalaska |
Aleutians | Unalaska | Water/Sewer | Complete and monitor water and wastewater plants | Finish construction and monitor efficiency of new water and wastewater plants | Active Project | Final Design & Construction | ANTHC |
Aleutians | Unalaska | Wind | Set up MET tower to test wind potential | Identify MET tower site | Active Project | Reconnaissance & Feasibility | City of Unalaska |
Bristol Bay | Aleknagik | Biomass | Biomass | Aleknagik sought a pre-feasibility study of biomass. | Previously Considered | Not Operational | City of Aleknagik |
Bristol Bay | Aleknagik | Energy Efficiency | Expand Wx/EE residential participation, public facilities | Increase use of weatherization and EE programs; incorporate EE into facility design. | Issue/Need | Need Identified | |
Bristol Bay | Aleknagik | Energy Infrastructure | Electric substation construction | Funding for substation construction; Consider energy when designing new public facilities. They will require energy which requires transmission lines and potentially more electrical capacity (3 phase). | Issue/Need | Need Identified | |
Bristol Bay | Aleknagik | Energy Infrastructure | Add additional community facilities to PCE program | Issue/Need | Need Identified | Aleknagik Traditional Council | |
Bristol Bay | Aleknagik | Solar | Explore solar PV for public facilities (laundry, landfill) | Issue/Need | Need Identified | City of Aleknagik | |
Bristol Bay | Aleknagik | Water/Sewer | Upgrade piped septic system | Piped septic system needs upgrade, 27 years old and does not connect to all homes in community. | Issue/Need | Need Identified | City of Aleknagik |
Bristol Bay | Aleknagik | Wind | Install anemometer for wind data collection | Previously Considered | Not Operational | ||
Bristol Bay | Chignik Bay | Energy Efficiency | New round of weatherization needed | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Bay | Energy Infrastructure | Repair transmission lines | Transmission lines need attention; requested lineman through AEA, never heard a response | On Hold | Need Identified | |
Bristol Bay | Chignik Bay | Energy Infrastructure | Chignik intertie project | Previously studied, interest remains in connecting three communities via intertie to take advantage of renewable power | Previously Considered | Need Identified | |
Bristol Bay | Chignik Bay | Energy Infrastructure | Address high line loss | Line loss at high levels up to 11% | Issue/Need | Need Identified | |
Bristol Bay | Chignik Bay | Hydroelectric | Expand Indian Creek hydro and upgrade powerhouse | Restoring 60 kW Indian Creek system. 520 kW facility proposed. Upgrade existing powerhouse and address outstanding issues. | Active Project | Design | City of Chignik Bay |
Bristol Bay | Chignik Bay | Hydroelectric | Hydroelectric project | The ANTHC Rural Energy Initiative is working with the Lake And Peninsula Borough and the City of Chignik Bay to develop a hydroelectric project for the city of Chignik Bay. | Active Project | Design | City of Chignik Bay and Lake & Pen Borough |
Bristol Bay | Chignik Bay | Management | Hire subregional electric lineman | Subregional lineman – on call to deal with routine maintenance and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Chignik Bay | Water/Sewer | Water reservoir and distribution system repair | Water reservoir is falling apart, expected fix in April 2015; Water/sewer Leaks – pipes need to be updated | Active Project | Need Identified | |
Bristol Bay | Chignik Lagoon | Energy Efficiency | Community-wide Energy Efficiency | Looking at EE projects throughout community | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Energy Infrastructure | Add additional community facilities to PCE program | Increase use of PCE, probably missing a few buildings | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Energy Infrastructure | Transmission and distribution line repair and upgrades | Transmission lines are in poor condition; need look at distribution lines as well; upgrade needed for metering | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Energy Infrastructure | Chignik intertie project | Previously studied, interest remains in connecting three communities via intertie to take advantage of renewable power | Previously Considered | Need Identified | |
Bristol Bay | Chignik Lagoon | Energy Infrastructure | New fuel truck needed | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lagoon | Energy Infrastructure | Re-size generators for increased efficiency | Re-size generators to ensure efficient electricity production | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Geothermal | Geothermal and/or ground source heat pump reconnaissance | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lagoon | Heat Recovery | Heat recovery | System installed at diesel power plant, heats school. | Work Complete | Operational | Chignik Lagoon Village Council |
Bristol Bay | Chignik Lagoon | Hydro to Heat | Hydro to heat project (school, pool, greenhouse) | Install electric boiler for school and look at expanding for school pool and greenhouse. | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Hydroelectric | Packer's Creek Hydro | 177 kW run-of-river with 9-ft dam. | Active Project | Operational | Chignik Lagoon Village Council |
Bristol Bay | Chignik Lagoon | Management | Hire subregional electric lineman | Subregional lineman – on call to deal with routine maintenance and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Natural Gas | Natural gas exploration in N. Aleutian basin | Interest in natural gas drilling in North Aleutian sedimentary basin | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Transportation | Address erosion on hydro access road | Erosion is a problem on access road to hydro facility | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Transportation | Airport lighting and runway expansion | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lagoon | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lagoon | Wind | Wind study | 2 met towers installed & studies completed in 2005 & 2011. | Previously Considered | Reconnaissance & Feasibility | Chignik Lagoon Village Council |
Bristol Bay | Chignik Lake | Energy Efficiency | Expand residential and community energy efficiency | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lake | Energy Infrastructure | Chignik intertie project | Previously studied, interest remains in connecting three communities via intertie to take advantage of renewable power | Previously Considered | Need Identified | |
Bristol Bay | Chignik Lake | Energy Infrastructure | Address high line loss | Line loss at high levels up to 10% | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Energy Infrastructure | Replace powerhouse generators | 2 new generators needed | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lake | Geothermal | Investigate geothermal and/or ground source heat pumps | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lake | Heat Recovery | Heat recovery at school | System installed at power plant provides heat to school. | Work Complete | Operational | Chignik Lake Village Council |
Bristol Bay | Chignik Lake | Hydroelectric | Explore hydro possibilities | Issue/Need | Need Identified | ||
Bristol Bay | Chignik Lake | Management | Hire subregional electric lineman | Subregional lineman – on call to deal with routine maintenance and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Natural Gas | Natural gas exploration in N. Aleutian basin | Interest in natural gas drilling in North Aleutian sedimentary basin | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Solar | Residential and community solar PV | Install solar PV arrays on residences and community buildings | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Water/Sewer | Water and sanitation system upgrade | ||||
Bristol Bay | Chignik Lake | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and remote monitoring. | Issue/Need | Need Identified | |
Bristol Bay | Chignik Lake | Wind | Investigate wind resource at additional sites | Met tower removed in 2011, interested in exploring wind potential at other sites | Previously Considered | Reconnaissance & Feasibility | Chignik Lake Village Council |
Bristol Bay | Clark's Point | Biomass | Biomass heat loop (community center, CPVC, city office) | Work Complete | Operational | City of Clark's Point | |
Bristol Bay | Clark's Point | Energy Efficiency | LED streetlight upgrade (operational) | 5 LED streetlights installed | Work Complete | Operational | |
Bristol Bay | Clark's Point | Energy Efficiency | EE upgrades at new council building | New council building highly efficient with LED lights, toyo space heating & water heating | Work Complete | Operational | Clarks Point Village Council |
Bristol Bay | Clark's Point | Energy Infrastructure | AMPY meters installed | Work Complete | Operational | ||
Bristol Bay | Clark's Point | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Work Complete | Operational | ||
Bristol Bay | Clark's Point | Energy Infrastructure | Replace transformers to address high line loss | Line Loss at 14.9% in FY 2015. Replacing transformers to address. | Active Project | Installation | |
Bristol Bay | Clark's Point | Energy Infrastructure | Power Plant upgrades | AEA-funded power plant upgrades | Active Project | Repair & Upgrade | |
Bristol Bay | Clark's Point | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Bristol Bay | Clark's Point | Wind | 7 small wind turbines | On Hold | Installation | Clark's Point Village Council | |
Bristol Bay | Clark's Point | Wind | Wind to cold reconnaissance for ice production | Interest in wind to cold for ice production during fishing season | Issue/Need | Need Identified | Clark's Point Village Council |
Bristol Bay | Dillingham | Biomass | Landfill incinerator | Work Complete | Operational | City of Dillingham | |
Bristol Bay | Dillingham | Biomass | Biomass reconnaissance and feasibility study | Studies on interest and wood availability completed. | Active Project | Reconnaissance & Feasibility | City of Dillingham/BBNA |
Bristol Bay | Dillingham | Energy Efficiency | Energy efficiency retrofits – buildings and water and sewer systems | City Buildings & System retrofits. Library – boiler retrofits; water and waste water treatment plants EE upgrades | Active Project | Installation | City of Dillingham |
Bristol Bay | Dillingham | Energy Efficiency | LED or solar streetlight upgrade | Previously Considered | Need Identified | City of Dillingham | |
Bristol Bay | Dillingham | Energy Efficiency | EE lighting upgrade (T12 to LED) | Interior light switch out from T12s to LEDs | Issue/Need | Need Identified | City of Dillingham |
Bristol Bay | Dillingham | Energy Efficiency | EE&C awareness and EE upgrades (residential, public, commercial) | Increase education & awareness on EE and building energy use; improve EE of homes, businesses and public buildings, promote energy conservation in heating, electricity, & transportation | Issue/Need | Need Identified | |
Bristol Bay | Dillingham | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Issue/Need | Need Identified | ||
Bristol Bay | Dillingham | Energy Infrastructure | Distributed/shared energy systems pilot studies (small subdivisions, campuses) | Interest in pilot studies for distributed energy systems; Determine a practical strategy and possible incentives to develop shared energy systems within small subdivisions and commercial campuses. | Issue/Need | Need Identified | |
Bristol Bay | Dillingham | Heat Recovery | Heat recovery feasibility for ice production | Heat Absorption: Determining technical and economic feasibility of capturing excess heat from school (when in session) for ice making during summer/fishing season | Previously Considered | Reconnaissance & Feasibility | SWAMC |
Bristol Bay | Dillingham | Heat Recovery | Heat Recovery System installed at power plant provides excess heat to school, court, DOT, and utility buildings | Active Project | Operational | NEC | |
Bristol Bay | Dillingham | Management | Explore feasibility of multiple renewable energy resources | Explore the feasibility of developing renewable sources of energy including wind, hydro, geothermal, biomass, tidal, and solar; and of developing non-diesel sources of energy including peat and natural gas; Work with Nushagak Cooperative, Choggiung and ot | Issue/Need | Need Identified | |
Bristol Bay | Dillingham | Solar | Solar PV installation (BB campus, USFW, commercial) | Solar arrays on UAF Bristol Bay Campus, USFW building, and commercial buildings. | Active Project | Operational | City of Dillingham |
Bristol Bay | Egegik | Energy Infrastructure | LED streetlight upgrade | Active Project | Repair & Upgrade | ||
Bristol Bay | Egegik | Energy Infrastructure | Add community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Egegik | Energy Infrastructure | Address moderate line loss | Line loss at 7% in FY15 | Issue/Need | Need Identified | |
Bristol Bay | Egegik | Energy Infrastructure | Electric distribution line upgrade | Work Complete | Repair & Upgrade | ||
Bristol Bay | Egegik | Heat Recovery | Heat recovery at school and community center | System installed at power plant provides heat to school and community center. | Work Complete | Operational | City of Egegik |
Bristol Bay | Egegik | Management | Plan for impacts of greater EE on small power systems | Anticipate and plan for impacts of efficiency in very small communities; A lot of villages are getting smaller – if people get too efficient, it gets harder to get fuel deliveries | Issue/Need | Need Identified | |
Bristol Bay | Egegik | Solar | Solar thermal feasibility (residential and community building) | Interest in solar panels for heating water – residential and community buildings | Issue/Need | Need Identified | |
Bristol Bay | Egegik | Wind | Repairs to existing wind turbine at corporation office building. | Turbine is not operational and no longer under warranty. Would need additional funding to send out mechanic from Susitna Energy to repair. | Issue/Need | Not Operational | |
Bristol Bay | Egegik | Wind | Feasibility of Wind | AEA-funded wind feasibility study completed by V3 Energy. Determined not economically feasible. | Previously Considered | Reconnaissance & Feasibility | Lake and Peninsula Borough |
Bristol Bay | Ekwok | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Issue/Need | Need Identified | ||
Bristol Bay | Ekwok | Energy Infrastructure | Ekwok-New Stuyahok intertie | Intertie between Ekwok & New Stuyahok to capitalize on economies of scale; connect Ekwok to renewable generation once New Stuyahok’s wind project is operational | Work Complete | Operational | |
Bristol Bay | Ekwok | Energy Infrastructure | Address moderate line loss | Line loss at 6% in FY15 | Issue/Need | Need Identified | |
Bristol Bay | Ekwok | Transportation | Ekwok to New Stuyahok road | Issue/Need | Need Identified | ||
Bristol Bay | Ekwok | Water/Sewer | Sanitation system energy audit | ANTHC will be conducting an energy audit on their sanitation system by December 2018, with funding from the Denali Commission | Active Project | Repair & Upgrade | |
Bristol Bay | Igiugig | Energy Efficiency | More weatherization in homes | Issue/Need | Need Identified | ||
Bristol Bay | Igiugig | Energy Efficiency | LED lighting upgrades | Village council completed LED switch out | Work Complete | Operational | |
Bristol Bay | Igiugig | Energy Efficiency | Energy efficiency for high energy users (clinic, fire hall) | Issue/Need | Need Identified | ||
Bristol Bay | Igiugig | Energy Efficiency | EE audit & retrofits of sanitation system | ANTHC Rural Energy Initiative has been funded to conduct an energy audit for the sanitation system; complete and implement recommendations; | Active Project | Operational | |
Bristol Bay | Igiugig | Energy Infrastructure | Re-locate bulk fuel tank farm | New site for bulk fuel tank farm, current site is eroding into river; new diesel delivery truck | Issue/Need | Need Identified | |
Bristol Bay | Igiugig | Energy Infrastructure | Address high line loss | Line loss at 16.7% in FY15, potential for significant savings. | Issue/Need | Need Identified | |
Bristol Bay | Igiugig | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Igiugig | Heat Recovery | Heat recovery at pump house and rec center buildings | System installed at power plant provides heat to pump house and recreational center buildings. | Active Project | Operational | Igiugig Electric |
Bristol Bay | Igiugig | Hydroelectric | In-river electricity generation (pilot project) | Hydrokinetic: Pilot project using 25 kW turbine for in-river electricity generation. | Active Project | Reconnaissance & Feasibility | Igiugig Village Council |
Bristol Bay | Igiugig | Management | Identify funds for generator training | Generator training – funding for AVTEC or regional training | Issue/Need | Need Identified | |
Bristol Bay | Igiugig | Solar | Expand small-scale solar on homes and businesses | More solar for residences and community buildings | Issue/Need | Need Identified | |
Bristol Bay | Igiugig | Solar | Solar thermal installed on 3 buildings | Active Project | Operational | ||
Bristol Bay | Igiugig | Water/Sewer | Sanitation system energy audit | ANTHC will be conducting an energy audit on their sanitation system by December 2018, with funding from the Denali Commission | Active Project | Repair & Upgrade | |
Bristol Bay | Igiugig | Wind | Vertical axis wind turbines (pilot project) | 6 – 1.2 kW vertical axis wind turbines installed as pilot project. If proven, will be expanded. | Active Project | Monitor Developments | Village Council of Igiugig |
Bristol Bay | Iliamna | Biomass | Investigate biomass heat options | Pre-feasibility completed in 2013. Investigated heating village office and adjacent shop building. Not viable at time, but further investigation continuing. | Active Project | Monitor Developments | Iliamna Village Council |
Bristol Bay | Iliamna | Energy Efficiency | Build energy-efficient community building | Issue/Need | Need Identified | ||
Bristol Bay | Iliamna | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Iliamna | Transportation | Bridge between Iliamna and Nondalton | Bridge between Iliamna and Nondalton; Dock/Barge landing & staging area in Iliamna | Issue/Need | Need Identified | |
Bristol Bay | Iliamna | Wind | Wind Turbines | 3 wind turbines were pruchased within the last three years. Thay have not been installed yet due to discrepancy with the person who was supposed to help; they ended up not coming out. | On Hold | Installation | Iliamna Village Council |
Bristol Bay | King Salmon | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Kokhanok | Biomass | Wood boiler heating village council and community buildings | A GARN cordwood boiler heats Kokhanok Village Council Building and the Community Building. | Active Project | Operational | Lake and Peninsula Borough |
Bristol Bay | Kokhanok | Energy Infrastructure | New fuel truck needed | Issue/Need | Need Identified | ||
Bristol Bay | Kokhanok | Energy Infrastructure | Address line loss | Line loss at 7% in FY15, potential for savings. | Issue/Need | Need Identified | |
Bristol Bay | Kokhanok | Energy Infrastructure | Replace powerline cables | Issue/Need | Need Identified | ||
Bristol Bay | Kokhanok | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Kokhanok | Heat Recovery | Heat recovery at school | System installed at power plant provides excess heat to school. | Active Project | Operational | City of Kokhanok |
Bristol Bay | Kokhanok | Management | Hire subregional on-call utility operator | Need subregional on-call utility operator, fully trained and able to have full-time work by responding to regular needs and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Kokhanok | Solar | Explore small-scale solar on homes and community buildings | Issue/Need | Need Identified | ||
Bristol Bay | Kokhanok | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Bristol Bay | Kokhanok | Water/Sewer | Repair and upgrade water system | ANTHC currently working on complete change out for aging water system | Active Project | Repair & Upgrade | |
Bristol Bay | Kokhanok | Wind | Refurbishment of existing wind-diesel power plant. | Upgrade existing diesel system (replace generator with larger unit), upgrade controls/switchgear for automation; Integrate wind system to restore full functionality | Active Project | Final Design & Construction | Kokhanok Village Council, Lake and Peninsula Borough |
Bristol Bay | Koliganek | Energy Infrastructure | Address 9% line loss | Line loss at 9% in FY15 | Issue/Need | Need Identified | |
Bristol Bay | Koliganek | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Koliganek | Heat Recovery | Heat Recovery system provides heat to school, clinic & city offices | Work Complete | Operational | Koliganek Village Council | |
Bristol Bay | Koliganek | Transportation | Identify alternative means for fuel delivery | Low water levels make barging in fuel increasingly difficult, now considering flying in fuel | Issue/Need | Need Identified | |
Bristol Bay | Koliganek | Water/Sewer | Upgrade water and sewer system | There are many leaks and there are homes that don’t have any water or sewer; water quality is being monitored for 2nd year | Issue/Need | Need Identified | |
Bristol Bay | Koliganek | Water/Sewer | Sanitation system EE improvements and operator training | EE improvements, including LED lighting, boiler tuning, controls upgrades, and minor weatherization. Koliganek will also have the opportunity to send an operator to a two week operator training course at AVTEC as part of funding. | Active Project | Installation | |
Bristol Bay | Koliganek | Wind | Wind system | Draft CDR complete for wind and heat recovery system. | Active Project | Design | Koliganek Village Council |
Bristol Bay | Levelock | Energy Infrastructure | Address high line loss | Line loss at 17.7% in FY15, potential for significant savings. | Issue/Need | Need Identified | |
Bristol Bay | Levelock | Energy Infrastructure | Expand electricity distribution system | Additional powerlines needed for more residents | Issue/Need | Need Identified | |
Bristol Bay | Levelock | Energy Infrastructure | Identify funding for fish processing plant self-generation | Work Complete | Operational | ||
Bristol Bay | Levelock | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Levelock | Heat Recovery | Heat provided to school | System installed at power plant provides excess heat to school. Installed 2008. | Active Project | Operational | Levelock Electric |
Bristol Bay | Levelock | Heat Recovery | Heat recovery feasibility for ice production | Investigate heat absorption for flash freezing; technology currently used at larger scale but need pilot project for small scale use | Active Project | Reconnaissance & Feasibility | |
Bristol Bay | Levelock | Management | Hire subregional on-call utility operator | Subregional on-call utility operator, fully trained and able to have full-time work by responding to regular needs and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Levelock | Transportation | Address erosion's effect on dock infrastructure | Plan for erosion affecting river front and dock infrastructure | Issue/Need | Need Identified | |
Bristol Bay | Levelock | Wind | Wind feasibility | Investigating sites for wind project. | Active Project | Reconnaissance & Feasibility | Lake and Peninsula Borough |
Bristol Bay | Manokotak | Energy Efficiency | New energy efficient community building | Community building recently built using EE design and construction | Work Complete | Operational | |
Bristol Bay | Manokotak | Energy Efficiency | CFL lighting upgrade in homes and community buildings | Work Complete | Operational | ||
Bristol Bay | Manokotak | Energy Efficiency | LED streetlight upgrade | Work Complete | Operational | ||
Bristol Bay | Manokotak | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Manokotak | Energy Infrastructure | Address line loss & improve reporting | Community line loss not reported in 2014; significant savings may be available but requires complete reporting | Issue/Need | Need Identified | |
Bristol Bay | Manokotak | Energy Infrastructure | Small generator booster upgrade | Booster installed for small generators to increase the powerline voltage, distribute greater distances and reduce line loss | Work Complete | Operational | |
Bristol Bay | Manokotak | Heat Recovery | Install heat recovery system | Issue/Need | Need Identified | ||
Bristol Bay | Manokotak | Transmission | Manokotak to Dillingham Intertie | Issue/Need | Need Identified | Village and City | |
Bristol Bay | Manokotak | Transportation | Manokotak to Dillingham Road | Active Project | Reconnaissance & Feasibility | ||
Bristol Bay | Manokotak | Water/Sewer | Sanitation system energy audit | ANTHC will be conducting an energy audit on their sanitation system by December 2018, with funding from the Denali Commission | Active Project | Repair & Upgrade | |
Bristol Bay | Manokotak | Wind | Investigate alternative wind sites | Met tower installed in 2009, found level 2 wind class. | Active Project | Reconnaissance & Feasibility | City of Manokotak |
Bristol Bay | Naknek | Energy Efficiency | EE upgrades and new boilers at clinic | EE upgrades on clinic – new boilers and control system | |||
Bristol Bay | Naknek | Energy Efficiency | Improve energy efficiency of school buildings | Increase EE of school buildings is top priority, working on a proposal for funding, Additional weatherization | Issue/Need | Need Identified | |
Bristol Bay | Naknek | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Naknek | Energy Infrastructure | Address line loss | Line loss at 8.3% in FY15 | Issue/Need | Need Identified | |
Bristol Bay | Naknek | Heat Recovery | Investigate stack heat recovery | NEA: Investigate stack heat recovery, increasing capacity by using same BTU from diesel | Issue/Need | Need Identified | NEA |
Bristol Bay | Naknek | Heat Recovery | Investigate heat absorption for ice production | NEA: Investigate heat absorption for ice production in summer | Issue/Need | Need Identified | NEA |
Bristol Bay | Naknek | Heat Recovery | Heat Recovery to school and adjacent homes | System installed at power plant provides excess heat to school and a few adjacent homes. | Active Project | Operational | NEA/Bristol Bay Borough |
Bristol Bay | Naknek | Management | Net metering, integrating renewable energy production with the grid | Net metering, integrating renewable energy production with the grid | Issue/Need | Need Identified | |
Bristol Bay | Naknek | Solar | 80.08 kW solar array at Pedersen Point | 80.08 kW solar array moved from school to field near Pedersen Point. | Active Project | Operational | Naknek Electric Association |
Bristol Bay | Naknek | Transmission | Regional intertie (NEA and NEC) | Interest in intertie between NEA and NEC | Issue/Need | Need Identified | |
Bristol Bay | New Stuyahok | Biomass | Install wood boilers and high efficiency wood stove to heat community building | Pre-feasibility study completed in 2013 for cordwood system. | Active Project | Reconnaissance & Feasibility | Stuyahok Limited |
Bristol Bay | New Stuyahok | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | New Stuyahok | Energy Infrastructure | Ekwok-New Stuyahok Intertie | Intertie between Ekwok & New Stuyahok to capitalize on economies of scale; connect Ekwok to renewable generation once New Stuyahok’s wind project is operational | Work Complete | Operational | |
Bristol Bay | New Stuyahok | Energy Infrastructure | Improve fuel storage and transportation | Additional work on fuel storage and transport planned, but no current funding | Active Project | Need Identified | |
Bristol Bay | New Stuyahok | Heat Recovery | Heat school with excess heat from power plant | Active construction to capture recovered heat from the AVEC power plant cooling system by installing heat exchangers at the plant and school boiler module and 700 feet of underground piping. | Active Project | Installation | AVEC/SRSD |
Bristol Bay | New Stuyahok | Transportation | Road from Ekwok to New Stuyahok | Issue/Need | Need Identified | ||
Bristol Bay | New Stuyahok | Transportation | Investigate alternative fuel transport | River used for fuel transport to New Stuyahok has low water, it is easier to bring fuel via barge to Ekwok. | Issue/Need | Need Identified | |
Bristol Bay | New Stuyahok | Water/Sewer | Upgrade water and sewer lines | Issue/Need | Need Identified | ||
Bristol Bay | New Stuyahok | Water/Sewer | Sanitation system EE upgrades & solar PV project | Energy Efficiency upgrades will be completed in the community sanitation system by October 2017. The project will also install a solar PV system for the washeteria/water treatment plant. | Active Project | Installation | City of New Stuyahok |
Bristol Bay | New Stuyahok | Wind | 300 kW wind project | Feasibility assessment for a proposed 300kW wind project with associated integration components. | AVEC | ||
Bristol Bay | Newhalen | Energy Efficiency | LED streetlights | 20 LED streetlights installed | |||
Bristol Bay | Newhalen | Energy Efficiency | On-demand electric hot water heaters in schools, fire hall, clinic | Working with schools in Newhalen and Nondalton (also fire hall and clinic) to put in on-demand electric hot water heater. | Active Project | Operational | |
Bristol Bay | Newhalen | Energy Efficiency | Energy efficiency remodel of school building and gym | Increased energy efficiency by remodeling school and school gym | Work Complete | Operational | |
Bristol Bay | Newhalen | Energy Infrastructure | Add more community facilities to PCE program | Issue/Need | Need Identified | ||
Bristol Bay | Newhalen | Energy Infrastructure | Address high line loss | INNEC: Line loss at 11% in FY 15, due to old transmission system. | Issue/Need | Need Identified | |
Bristol Bay | Newhalen | Hydro to Heat | Dispatchable boilers heat city office and fire hall with excess electricity from Tazimina Hydro | Dispatchable boilers connected to hydro plant provide heat to city office and fire hall. | Active Project | Operational | |
Bristol Bay | Newhalen | Hydroelectric | Tazimina Run-of-River Hydro | 824 kW run-of-river project | Active Project | Repair & Upgrade | INNEC |
Bristol Bay | Newhalen | Water/Sewer | Sanitation system EE upgrades & solar PV system for washeteria/water treatment plant | Energy Efficiency upgrades will be completed in the community sanitation system by October 2017. The solar PV system will produce electricity for the washeteria/water treatment plant. | Active Project | Installation | City of Newhalen |
Bristol Bay | Nondalton | Biomass | Install high efficiency wood stoves at tribal office, community building, and St. Nicholas Church | Pre-feasibility completed in 2013 for installing high efficiency wood stoves at tribal office, community building, and St. Nicholas Church. | Active Project | Installation | City and Village |
Bristol Bay | Nondalton | Energy Efficiency | Energy efficiency upgrades to sanitation system | ANTHC Sanitation EE Upgrades/Training | Active Project | Installation | |
Bristol Bay | Nondalton | Energy Infrastructure | Upgrade submarine power cable to Nondalton | INNEC: Upgrade distribution infrastructure Newhalen to Nondalton – replace with armored submarine cable | Issue/Need | Need Identified | |
Bristol Bay | Nondalton | Hydro to Heat | Dispatchable boilers heat community buildings with excess electricity from Tazimina Hydro | Dispatchable electric boilers capturing excess electricity from hydro facility & converting to heat installed in Newhalen & Nondalton. | Active Project | Operational | |
Bristol Bay | Nondalton | Management | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Nondalton | Transportation | Bridge between Iliamna and Nondalton | Bridge between Iliamna and Nondalton; Dock/Barge landing & staging area in Iliamna | Issue/Need | Need Identified | |
Bristol Bay | Nondalton | Water/Sewer | Sanitation system EE upgrades and operator training | Sanitation system EE improvements, including LED lighting, boiler tuning, controls upgrades, and minor weatherization, were implemented in 2015. | Work Complete | Installation | |
Bristol Bay | Nondalton | Water/Sewer | Replacement of old water system | Water system – half replaced in project with ANTHC but remaining old system has serious leaks (losing up to 70,000 gallons of water per day) | On Hold | Installation | |
Bristol Bay | Nondalton | Wind | Wind Turbines | Wind turbines and solar panels to be installed in spring of 2017. Need to purchase additional foundation. | On Hold | Installation | Nondalton Tribal Council |
Bristol Bay | Pedro Bay | Energy Infrastructure | Address line loss | Line loss at 9.2% in FY15, potential for significant savings. | Issue/Need | Need Identified | |
Bristol Bay | Pedro Bay | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Pedro Bay | Heat Recovery | Heat multiple community buildings with excess heat from power plant | Heat Recovery: System installed at power plant provides excess heat to multiple community buildings; originally connected to school which closed. | Work Complete | Operational | Pedro Bay Village Council |
Bristol Bay | Pedro Bay | Hydroelectric | Knutson Creek Hydro, 150 kW run-of-river | Active Project | Design | Pedro Bay Village Council | |
Bristol Bay | Pedro Bay | Management | Hire subregional on-call utility operator | Subregional on-call utility operator, fully trained and able to have full-time work by responding to regular needs and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Pedro Bay | Solar | Expand use of solar thermal | Issue/Need | Need Identified | ||
Bristol Bay | Pedro Bay | Transportation | Extend airport runway, enable larger shipments of fuel | Airport extension to enable larger shipments of fuel | Issue/Need | Need Identified | |
Bristol Bay | Perryville | Energy Efficiency | Weatherization needed in older homes | Issue/Need | Need Identified | ||
Bristol Bay | Perryville | Energy Infrastructure | RPSU – New powerhouse | New powerhouse now successfully integrates the 10 small wind turbines with the grid, hooks up disptachable heat to heat the school with excess wind, and additionally heats the school through a heat recovery system on the generators. | Work Complete | Operational | |
Bristol Bay | Perryville | Energy Infrastructure | Address high line loss | Line loss at high levels up to 22% in previous years in Perryville, significant savings are available | Issue/Need | Need Identified | |
Bristol Bay | Perryville | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Perryville | Heat Pumps | Increase buildings for which ground source heating is available | Expand buildings to which ground source heating is available | Active Project | Operational | |
Bristol Bay | Perryville | Heat Recovery | Heat school buildings with excess heat from power plant | System installed at power plant provides excess heat to the school. | Work Complete | Operational | Perryville Village Council |
Bristol Bay | Perryville | Management | Hire subregional lineman | Subregional lineman – on call to deal with routine maintenance and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Perryville | Solar | 3 kW solar array on community building | Active Project | Operational | Native Village of Perryville | |
Bristol Bay | Perryville | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Bristol Bay | Perryville | Wind | 10 residential (2.5-2.9 kW each) wind turbines | 10 residential (2.5-2.9 kW each) turbines installed. | Work Complete | Operational | Village Council of Perryville |
Bristol Bay | Pilot Point | Energy Efficiency | Improve energy efficiency in homes – weatherization or build new | More weatherization needed; unsure if best to tear down or weatherize dilapidated homes | Issue/Need | Need Identified | |
Bristol Bay | Pilot Point | Energy Infrastructure | Address high line loss | Line loss at 10% in FY15, potential for significant savings. | Issue/Need | Need Identified | |
Bristol Bay | Pilot Point | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Pilot Point | Energy Infrastructure | Install back-up generator | No back-up power at present | Issue/Need | Need Identified | |
Bristol Bay | Pilot Point | Energy Infrastructure | Install meter boxes on homes, upgrade distribution lines and transformers | Install meter boxes on homes, upgrade distribution lines and transformers | Issue/Need | Need Identified | |
Bristol Bay | Pilot Point | Heat Recovery | Heat school with excess heat from power plant | System installed at power plant provides excess heat to the school. | Work Complete | Operational | Pilot Point Electric |
Bristol Bay | Pilot Point | Heat Recovery | Waste Heat | Want to install a heat loop between community buildings and power plant. | Active Project | Installation | Pilot Point Tribal Council |
Bristol Bay | Pilot Point | Wind | Integrate 100 kW wind farm into city grid | 100 kW wind farm with dispatchable electric boiler, powerhouse upgrades needed to integrate the wind farm into the Pilot Point grid. | Active Project | Installation | City & Village of Pilot Point |
Bristol Bay | Port Alsworth | Energy Infrastructure | Address line loss | Line loss above 6% in FY15, potential for savings | Issue/Need | Need Identified | |
Bristol Bay | Port Alsworth | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Port Alsworth | Heat Recovery | Heat old school, duplex, and teacher's house with excess heat from power plant | System installed at power plant provides excess heat to old school, duplex, and teacher's house. | Active Project | Operational | Tanalian Electric Cooperative |
Bristol Bay | Port Alsworth | Management | Hire subregional on-call utility operator | Subregional on-call utility operator, fully trained and able to have full-time work by responding to regular needs and emergencies | Issue/Need | Need Identified | |
Bristol Bay | Port Alsworth | Solar | Add solar arrays to residences and public buildings | Issue/Need | Need Identified | ||
Bristol Bay | Port Alsworth | Transportation | Public airstrip would reduce freight/fuel costs | Public airstrip would reduce freight/fuel costs | Issue/Need | Need Identified | |
Bristol Bay | Port Heiden | Energy Infrastructure | Improve reporting on line loss | Community line loss not reported in 2015; significant savings may be available but requires complete reporting | Issue/Need | Need Identified | |
Bristol Bay | Port Heiden | Energy Infrastructure | Re-locate fuel tanks, avoid erosion | Bulk fuel tanks on edge of eroding area, solution needed ASAP | Issue/Need | Need Identified | |
Bristol Bay | Port Heiden | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Port Heiden | Geothermal | Geothermal project, install temperature monitor wells | Continue geothermal project pre-feasibility study, need more temperature monitor wells | Issue/Need | Reconnaissance & Feasibility | |
Bristol Bay | Port Heiden | Heat Recovery | Heat fire department and VPSO buildings with excess heat from power plant | System installed at power plant provides excess to the fire department and VPSO buildings. | Work Complete | Operational | Port Heiden Utilities |
Bristol Bay | Port Heiden | Hydroelectric | Conduct new study on hydro potential | Issue/Need | Need Identified | ||
Bristol Bay | Port Heiden | Wind | High penetration 330 kW wind project | LPB proposed a high penetration 330 kW design and construction project. | Active Project | Design | Lake and Peninsula Borough |
Bristol Bay | South Naknek | Energy Efficiency | Energy audits of sanitation system and community buildings. | The ANTHC Rural Energy Initiative conducted energy audits of the sanitation system, health clinic, community center, and tribal office in 2011. | Work Complete | Repair & Upgrade | |
Bristol Bay | South Naknek | Energy Efficiency | Weatherization and energy efficiency | Weatherization and energy efficiency | Issue/Need | Need Identified | |
Bristol Bay | South Naknek | Wind | Investigate wind power | Investigate wind power | Issue/Need | Need Identified | |
Bristol Bay | Togiak | Energy Efficiency | Wx upgrades (multi-use bldg, sr center, clinic) (operational) | Rehabbed public buildings: multiuse building & heating system in Senior Center & Clinic replaced | Work Complete | Operational | |
Bristol Bay | Togiak | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Togiak | Energy Infrastructure | Twin Hills and Togiak intertie | Interest in intertie connecting Twin Hills and Togiak | Issue/Need | Need Identified | |
Bristol Bay | Togiak | Energy Infrastructure | Bulk Fuel Tank Farm Refurbishment | Tank farm upgrade, tanks are old and threatened by erosion since it’s near the coast and the seawall. Upgrade wasn’t funded in the past due to environmental concerns. | Active Project | Repair & Upgrade | |
Bristol Bay | Togiak | Energy Infrastructure | Replace community building boilers (1-2 per year) | Plan to replace community building boilers with new, more efficient boilers. Aim is to replace 1 to 2 boilers per year. | Active Project | Reconnaissance & Feasibility | |
Bristol Bay | Togiak | Heat Recovery | Heat multiple buildings with excess heat from power plant | Heat recovery between AVEC power plant and multiple buildings: Water Treatment Plant, Clinic, Police Station, City Office, and Old School Community Activity Building. | Active Project | Final Design & Construction | City of Togiak |
Bristol Bay | Togiak | Hydroelectric | Explore options for low-velocity, small hydro | Explore options for low-velocity, small hydro | Issue/Need | Need Identified | |
Bristol Bay | Togiak | Water/Sewer | Upgrade/replace water and sewer lines | Water and sewer lines within township were put in 1974, Upgrade/Replacement needed | Issue/Need | Need Identified | |
Bristol Bay | Togiak | Water/Sewer | Sanitation system energy audit | ANTHC will be conducting an energy audit on their sanitation system by December 2018, with funding from the Denali Commission. | Active Project | Repair & Upgrade | City of Togiak |
Bristol Bay | Togiak | Wind | Wind study at alternative sites | Interest in testing on alternative site. There are land use issues – on private property & Native Corp land. | Previously Considered | Not Operational | City of Togiak |
Bristol Bay | Twin Hills | Energy Efficiency | Energy efficiency and weatherization for the whole village | Energy Efficiency and Weatherization work for the whole village | Issue/Need | Need Identified | Twin Hills Village |
Bristol Bay | Twin Hills | Energy Infrastructure | Improve reporting on line loss | Community line loss not reported in 2015; significant savings may be available but requires complete reporting | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Energy Infrastructure | Install low-maintenance generators | New, low-maintenance generators needed | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Energy Infrastructure | Add community facilities to PCE program (strong potential) | Strong potential to add more community facilities to the PCE program | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Heat Recovery | Install heat recovery system | Interest in installing heat recovery system | Previously Considered | Not Operational | |
Bristol Bay | Twin Hills | Solar | Add solar arrays to homes and community buildings | Add solar arrays to homes and community buildings | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Transmission | Twin Hills and Togiak intertie | Interest in intertie connecting Twin Hills and Togiak | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Transportation | Address multiple transportation concerns (barriers to barging fuel and road deterioration) | Low water on river making it increasingly difficult to barge in fuel; Road pads are on tundra and moss at risk of serious deterioration | Issue/Need | Need Identified | |
Bristol Bay | Twin Hills | Water/Sewer | Sanitation system energy audit | ANTHC conducted an energy audit on the community' s sanitation system in 2014. EE improvements for the community' s sanitation system were implemented in 2015. | Work Complete | Repair & Upgrade | |
Bristol Bay | Ugashik | Energy Infrastructure | Wind/Solar Upgrade | Current wind/solar power infrastructure is about 15 years old and showing its age. Community needs to upgrade system and power plant to keep up with current electrical demands. | Active Project | Repair & Upgrade | Ugashik Traditional Council |
Kodiak | Akhiok | Bulk Fuel | Upgrade tank farm | Issue/Need | Need Identified | ||
Kodiak | Akhiok | Energy Efficiency | Increase local education about energy efficiency | Active Project | Need Identified | ||
Kodiak | Akhiok | Energy Efficiency | EE upgrades to public buildings | Issue/Need | Need Identified | ||
Kodiak | Akhiok | Energy Infrastructure | Install AMPY smart meters in homes | Work Complete | Operational | ||
Kodiak | Akhiok | Energy Infrastructure | Upgrade generators and power distribution system | Fix frequency issues, upgrade generators and engines, and upgrade power distribution system | Issue/Need | Need Identified | |
Kodiak | Akhiok | Energy Infrastructure | Re-wire totalizing meter on powerhouse | The totalizing meter at the powerhouse needs to be re-wired. It was determined in October that the meter was wired into the bus incorrectly during installation. The utility needs a technician skilled in this task to come out and complete the job. | Scheduled | Repair & Upgrade | City of Akhiok |
Kodiak | Akhiok | Hydroelectric | Investigate feasibility of hydro | Issue/Need | Need Identified | ||
Kodiak | Akhiok | Management | Review utility financial management & PCE reporting | Assess the financial management of the utility and provide accurate costs to the RCA for correct PCE determination. | Active Project | Need Identified | |
Kodiak | Akhiok | Management | Train next generation utility operator | Active Project | Need Identified | ||
Kodiak | Akhiok | Other Critical Community Need | Residential energy efficienty – retrofits or new construction | Need for new, energy efficient homes. Some homes are so old that they shouldn’t even be retrofitted; they just need to be retired | Issue/Need | Need Identified | |
Kodiak | Akhiok | Transportation | Fuel truck to move fuel from tank farm to powerhouse | Issue/Need | Need Identified | ||
Kodiak | Akhiok | Transportation | Feasibility of road to Alitak Cannery | Issue/Need | Need Identified | ||
Kodiak | Akhiok | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Kodiak | Akhiok | Wind | Investigate wind resource, install MET towers | Issue/Need | Need Identified | ||
Kodiak | Karluk | Energy Efficiency | EE upgrades to public buildings | Issue/Need | Need Identified | ||
Kodiak | Karluk | Energy Efficiency | EE upgrades to residential buildings | EE upgrades to residential buildings. Find ways to help homeowners up-keep homes and lower home heating and electric bills. | Issue/Need | Need Identified | |
Kodiak | Karluk | Energy Infrastructure | Replace existing generators, expand generation capacity | Replace existing generators with larger capacity units, or one larger capacity unit and one smaller | Active Project | Repair & Upgrade | |
Kodiak | Karluk | Energy Infrastructure | Upgrade streetlights | Issue/Need | Need Identified | ||
Kodiak | Karluk | Heat Recovery | Investigate heat recovery system on powerhouse | Issue/Need | Need Identified | ||
Kodiak | Karluk | Water/Sewer | Replace and upgrade water lines and pump-house | Issue/Need | Need Identified | ANTHC | |
Kodiak | Kodiak City | Water/Sewer | Sanitation system energy audit | ANTHC Rural Energy Initiative has identified that this community's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades. | Issue/Need | Need Identified | |
Kodiak | Larsen Bay | Energy Efficiency | EE upgrades to public buildings | Issue/Need | Need Identified | ||
Kodiak | Larsen Bay | Energy Efficiency | EE upgrades to residential buildings | Active Project | Need Identified | ||
Kodiak | Larsen Bay | Energy Infrastructure | Replace electricity transmission lines | AEA Electrical Retrofit | Active Project | Repair & Upgrade | |
Kodiak | Larsen Bay | Energy Infrastructure | Broadband Internet Infrastructure | Active Project | Need Identified | ||
Kodiak | Larsen Bay | Heat Pumps | Investigate ground source heat pumps as alternative to diesel-heaters | Replace expensive diesel with ground source heat pumps | Active Project | Reconnaissance & Feasibility | |
Kodiak | Larsen Bay | Hydroelectric | Replace spillway and increase water supply to hydro facility | Update/Replace/Refurbish spillway and increase water supply to hydro | Scheduled | Reconnaissance & Feasibility | |
Kodiak | Larsen Bay | Management | Training to replace aging utility management/maintenance workers | Many young people move away from village. Having trouble finding replacements for maintenance workers who will need to retire eventually. | Issue/Need | Need Identified | City of Larsen Bay |
Kodiak | Larsen Bay | Transportation | Dock construction and moorage for fuel barge | Issue/Need | Reconnaissance & Feasibility | ||
Kodiak | Larsen Bay | Water/Sewer | Sanitation system energy audit and EE upgrades | ANTHC Rural Energy Initiative has identified that Larsen Bay's sanitation system would benefit from an energy audit and potentially energy efficiency upgrades | Issue/Need | Need Identified | |
Kodiak | Larsen Bay | Wind | Assess wind resource, integrate with hydroelectric system | Feasibility study of incorporating wind energy (MET tower) | Issue/Need | Need Identified | |
Kodiak | Old Harbor | Biomass | Biomass heating of community buildings | Community-wide integration of biomass | Active Project | Reconnaissance & Feasibility | The Alutiiq Tribe of Old Harbor |
Kodiak | Old Harbor | Energy Efficiency | EE upgrades to commercial buildings | Active Project | Need Identified | ||
Kodiak | Old Harbor | Energy Efficiency | EE upgrades to residential buildings | Issue/Need | Need Identified | ||
Kodiak | Old Harbor | Energy Efficiency | EE upgrades to public buildings | Active Project | Need Identified | ||
Kodiak | Old Harbor | Energy Infrastructure | Replace existing energy infrastructure | Replace and upgrade current infrastructure | Active Project | Repair & Upgrade | |
Kodiak | Old Harbor | Energy Infrastructure | Lighting for airport | Active Project | Need Identified | ||
Kodiak | Old Harbor | Hydroelectric | Hydro Project: Run of river facility and access road | Final design and construction funding for hydro. Access road for hydro. | Scheduled | Final Design & Construction | |
Kodiak | Old Harbor | Management | Train next generation utility operator | Workforce Development: Training for the next generation utility operator | Issue/Need | Need Identified | |
Kodiak | Old Harbor | Other Critical Community Need | Increase education about science and energy in schools | Increase local education about science and energy in schools | Issue/Need | Need Identified | |
Kodiak | Old Harbor | Transportation | Extend runway | Runway expansion project | Active Project | Final Design & Construction | |
Kodiak | Old Harbor | Transportation | Resurface local roads | Issue/Need | Need Identified | ||
Kodiak | Old Harbor | Water/Sewer | Replace and upgrade existing water and sewer infrastructure | Replace and upgrade current infrastructure | Active Project | Repair & Upgrade | |
Kodiak | Old Harbor | Wind | Investigate wind resource | Install MET tower | Active Project | Installation | |
Kodiak | Ouzinkie | Biomass | Investigate options for biomass system | Find funding for feasibility study of biomass system | On Hold | Reconnaissance & Feasibility | City of Ouzinkie |
Kodiak | Ouzinkie | Energy Efficiency | Install AMPY meters | Issue/Need | Need Identified | ||
Kodiak | Ouzinkie | Energy Efficiency | Replace street lights with LEDs | Replace street lights with LEDs as part of regular maintenance | Active Project | Installation | Ouzinkie Transportation Dept |
Kodiak | Ouzinkie | Energy Efficiency | EE upgrades to public buildings | EE upgrades to public building infrastructure | Active Project | Need Identified | |
Kodiak | Ouzinkie | Energy Infrastructure | Utility infrastructure (transformers, poles) breaking down | Issue/Need | Need Identified | ||
Kodiak | Ouzinkie | Heat Recovery | Utilize heat recovery & solar on potential new building. | Potential new equipment storage warehouse to be built next to power plant. Intention is to build the roof able to hold solar panels as well. | Issue/Need | Need Identified | |
Kodiak | Ouzinkie | Hydroelectric | Ouzinkie Hydroelectric, 125 kW – Replacement for failing penstock, an improved hydro turbine, and supporting equipment | Find funding to replace powerhouse and penstock | Active Project | Reconnaissance & Feasibility | City of Ouzinkie |
Kodiak | Ouzinkie | Solar | Analyze feasibility of small-scale solar power | City has expressed interest in potential solar panels on hoop house, new transportation warehouse | Active Project | Reconnaissance & Feasibility | City of Ouzinkie |
Kodiak | Ouzinkie | Wind | Analyze feasibility of small-scale wind power | Issue/Need | Monitor Developments | ||
Kodiak | Port Lions | Biomass | Community-wide biomass heating | Issue/Need | Monitor Developments | ||
Kodiak | Port Lions | Energy Efficiency | Implement Energy Efficiency retrofits to community buildings under DOE RACEE program | Active Project | Installation | City of Port Lions and Native Village of Port Lions | |
Kodiak | Port Lions | Energy Efficiency | EE upgrades to residential buildings | Issue/Need | Need Identified | ||
Kodiak | Port Lions | Energy Efficiency | EE upgrades to commercial buildings | Issue/Need | Need Identified | ||
Kodiak | Port Lions | Heat Pumps | Increase use of ground source heat pumps | Replace expensive diesel with ground source heat pumps | Active Project | Reconnaissance & Feasibility | |
Kodiak | Port Lions | Other Critical Community Need | Reactivate Tribal Energy Department | Issue/Need | Need Identified | City of Port Lions and Native Village of Port Lions | |
Kodiak | Port Lions | Other Critical Community Need | Broadband internet infrastructure | Issue/Need | Need Identified | City of Port Lions | |
Kodiak | Port Lions | Transportation | Improve reliability of low-cost transportation options | Improve reliability of cost effective transportation options – improve transportation options for elders | Issue/Need | Need Identified | |
Kodiak | Port Lions | Water/Sewer | Conduct energy audit on water system | Conduct system-wide energy audit on water system | Issue/Need | Repair & Upgrade | City of Port Lions |